2006-07
Renovations
Kitchen stripped of all fittings and walls removed (8 Dec 06)
Looking from main room towards the kitchen and back room.
Part of new aircon installed up on ceiling (8 Dec 06)
Back room/teaching room (8 Dec 06)
1st Dec - Bridge stopped one week earlier than normal to allow time for the builders to do as much work as possible before Xmas.

4th Dec - Renovations started in earnest.

11th Dec - The kitchen has been stripped of all fittings and start made to the drainage.  The kitchen walls from the main room and back room as well as the wall between these 2 rooms have been removed. The window at the front of the building has been removed and the new outside wall enclosed.  The old airconditioning units (inside and out) have been removed and some of the new system has been installed. The rest of the new system is on site, ready to go in.

News received today we have been successful in gaining more funding.  Our big thanks to the Pub Charities for their generuos donation.

Official opening for our new rooms and the start of the Jubilee year is planned for Feb 10th (at our first tournament).  There wil be a special guest, performing the honours !

17th Dec - Kitchen structure completed and partly gibbed. Framing for bifold doors installed. Aircon units installed. Framing for office completed. The kitchen is due to be installed Tuesday 19th ! Scroll down to see more photos

21 Dec - Kitchen mostly installed.  Aircon ducting for the back room installed.  Framing to lower ceiling in all rooms about 50% completed.  Office has insulation and electrical wiring completed and partly lined.  Progress has been rapid. Many thanks to everyone involved

20 Jan - Working Bee to clean up most of the rubbish and vacuum the floor. The airconditioning is completed, ceiling lights installed and a good portion of the batts and ceiling panels are in.  The majority of the painting has also been done.  Next week the lino in the kitchen and toilets will be done and carpet repaired/rejoined. It is expected that all jobs will be completed by the end of the week (26th Jan)

22 Jan - On Monday 5th Feb, our clubrooms will be open 6:30 pm for members to view the renovations, before the start of play.  Tea and coffee will be available from our new kitchen and the bar will be open

For all other sessions that week, the clubrooms will be open 1 hour before the start of play, so members can view the changes.

The official opening of the rooms
will be on the 10th February,
at our first tournament of the year.
His Worship the Mayor, Stuart Crosby will officiate the opening at approximately 9:45 am. 
All members are welcome to attend.

2 Feb, 2007 - We have finished !!!
Working bee is planned 3rd Feb to clean up the last of the rubbish and set up the room for play to start 5th Feb

WELL DONE EVERYONE
Click here to view an update of the funding
Aircon units to be installed (8 Dec 06)
New outside wall and office (8 Dec 06)
New office at front of room (8 Dec 06)
Aircon units installed. These will be concealed in the ceiling (15 Dec 06)
Kitchen looking towards the new servery and old office (now a storage room). New hotwater cylinder installed above storage room (15 Dec 06)
Outside of kitchen with new servery in the back room.  Includes part of the frame for bifold doors.  (15 Dec 06)
Office all framed up  (15 Dec 06)
Kitchen looking towards the back door, nearly all installed.
Framing for lower ceiling installed (21 Dec 06)
Kitchen looking towards the main room.  NB: the new centre work area the servery into both rooms and frame to lower ceiling (22 Dec 06)
Back room/teaching room new aircon installed (21 Dec 06)
Framing for lowered ceiling installed in the mainroom and rubbish removed (22 Dec 06)
Office partly lined, insulation and electrical wiring done  (21 Dec 06)
Working Bee - Back room/teaching room. ceiling partly completed
(20 Jan 07)
Aircon completed, new lights installed and ceiling with batts partly installed in the mainroom (20 Jan 07)
Office completed and painted. Trophy cabinet relocated  (20 Jan 07)
New outside wall and office (20 Jan 07)
Kitchen looking towards the main room. 
All completed with roller doors installed (2 Feb 07)
Kitchen looking towards the back. 
All completed with new commercial dishwasher installed (2 Feb 07)
Office and reception area completed, including sound system.  (2 Feb 07)
Ceiling, lights and internal sound system completed and 
carpet repaired in the mainroom. Airconditioner commissioned (2 Feb 07)
Outside of kitchen with new servery in the back room and roller doors installed.  Includes part bifold doors.  (02 feb 07)
Main room set up ready for bridge. 
Thanks to all who worked hard at the Working Bee (3 Feb 07)
Main room looking towards the office and reception area.  (3 Feb 07)